Contract included on-site calibrations of all process instrumentation, pressure gauges and temperature indicators associated with the Canola Oil Processing Facility. Mundial Group prepared individual calibration records for each device calibrated on-site. All test equipment met NIST standards. Calibration stickers were affixed to each instrument that was certified. Devices that were found to be out of tolerance were documented and reported to the client to have it repaired or replaced.
Explore More Case Studies
-
Operational & Functional Acceptance TestingControl System Pre-Commissioning
Sparks, NVContract includes pre-commissioning (OAT) support for HVAC and Process Control Systems throughout the current factory buildout.
-
Instrument CommissioningI&C Superintendents and Field Engineers
Sparks, NVMundial Group is providing augmented staffing to perform construction superintendent duties associated with the construction of the factory expansion project.