Case Studies
-
Operational & Functional Acceptance TestingControl System Pre-Commissioning
Sparks, NVContract includes pre-commissioning (OAT) support for HVAC and Process Control Systems throughout the current factory buildout.
-
Instrument CommissioningI&C Superintendents and Field Engineers
Sparks, NVMundial Group is providing augmented staffing to perform construction superintendent duties associated with the construction of the factory expansion project.
-
Operational & Functional Acceptance TestingAOP Water System Pre-Commissioning
Hillsboro, ORContract included pre-commissioning (OAT) support for 4 AOP (Advanced Oxidization Process) Systems.
-
Instrument CommissioningBoeing 777X Project
Everett, WAMundial Group is contracted to provide support for this Boeing 777X Wing Fabrication Facility.
-
Instrument CalibrationMichelin Red Oak / G83 Projects
Anderson, SCContract included on-site calibrations of all process instrumentation and control valves for the Michelin Tire Manufacturing Facility.
-
Instrument CalibrationPacific Coast Canola
Moses Lake, WAContract included on-site calibrations of all process instrumentation, pressure gauges and temperature indicators associated with the Canola Oil Processing Facility.